• Procurement
• Prefabrication at our own Pipe spool production Workshop
• Installation on Site
The project duration is estimated to be 1 year, with approximately 100 team members required.
LSEP is currently in the construction stage. Upon completion of the construction, the project is expected to be commissioned in 2025 and supply enough clean energy to power 125,000 households, offsetting 200,000 tons of carbon dioxide emissions (CO2) annually.
A team of 70 employees including Site Managers, Supervisors, QA/QC engineers, welders, fitters
• Welding and erection works
• Specific nuclear safety requirements and trainings met, medical books with radiation, etc.
• Installation of low-level, high-level and riser modules and spools
• Provision for pneumatic and hydraulic testing
• Prefabrication of stainless and carbon steel pipe spools
• Pipe and fittings ranging from DN15 to DN900
• Prefabrication of pipe supports and steel structures
• Welding supervision, inspection and control
• NDT control
• Preparation of quality documentation
• Painting and transportation
Core numbers:
– 18 500 m of welded pipe spools (60 000 dia inches);
– 210 000 kg of Carbon steel;
– 280 000 kg of Stainless steel;
– 40 trucks of our production.
•Installation of economizer mandoors;
•Replacement of one tertiary air damper plate and axle
•Blocking of hangers, supports, fix points, etc.
•Dismantling of valves, strainers, measurements and installation of temporary equipment (caps, blind flanges, etc.)
•Dismantling of existing pipes and installation of temporary bypass (DN 50- DN 500, Material 16Mo3 – 10CrMo9-10, few pipes are probably P91)
•Pressure tests of the defined piping and boiler circuits
•Reinstallation of all operational equipment
•Installation of economizer mandoors
•Replacement of one tertiary air damper plate and axle
•Replace load burner air damper
•Replacement of Fuel feeding chutes
•Installing new pipeline from bottom ash conveyor to boiler
•Replacement of mandoors
•Replace recirculation gas duct expansion
•Modification of air mixing duct
•Replacement of expansion bellows in fuel feeding lines
•Replacement of conveyer bottom plates
•Installing Hot-air flushing system
•Installation of new piping systems
•Welding, fitting, erection & lifting works
•Installation of piping supports
•NDT applications
•Documentation
•Project’s supervision services
• Prefabrication of pipe spools
• Erection of new Gas and Condensate piping
• Installation of static equipment
• Installation of supports and steel structures
• Welding, lifting & erection activities
• Pressure testing of new piping
• Preparation of quality / As build documentation
• Inspection of prefabricated pipe spools (prefabrication made by other contractor)
• Dismantling parts of old pipeline
• Dismantling old equipment and supports
• Installation of new piping
• Installation of supports and steel structures
• Replacement of columns, heat exchangers and pumps
• Welding, lifting & erection activities
• PWHT, NDT services
• Pressure testing of new piping
• Preparation of quality / As-build documentation
• Off site prefabrication & on site installation of pipe spools
• Installation of pipe supports
• Supply of materials
• Installation of static equipment including heat exchangers, drums, filters & pumps
• Welding, erection, NDT services
• Pressure testing of new piping
• Preparation of quality documentation and As-builds.
• Installation of new piping systems
• Welding, fitting, erection & lifting works
• Installation of piping supports
• NDT applications
• Documentation
• Project’s supervision services
• Installation of new stainless steel piping systems
• Welding, fitting, erection & lifting works
• Installation of piping supports
• NDT applications
• Documentation
• Project’s supervision services
• Prefabrication & installation of pipe spools & pipe supports
• Erection of pipelines
• Supply of materials
• Installation of static equipment
• Welding, erection, NDT works
• Insulation, painting works
• Pressure testing of new piping systems
• Preparation of quality documentation and As-build documentation
• Installation of two gas compressor stations
• Prefabrication of pipe spools
• Installation of pipe supports
• Welding, lifting & erection activities
• Installation of various equipment & apparatus
• Civil , supervision works
• Material & equipment delivery works
• Pressure testing of new piping
• Preparation of quality documentation and As-build documentation
• Commissioning & start-up
• Prefabrication of HP/LP Amin piping
• Erection & welding of prefabricated pipes
• Installation of pipelines in piperacks
• Internal mechanical works for reactor
• Heat treatment services
• QA/QC services
• Prefabrication of pipe spools & NDT application
• Assembly & installation of pipe supports
• Welding & fitting works
• Installation of gas pipeline
• Installation of pipe supports
• Erection of rotating equipment
• Erection & welding of prefabricated pipes
• Boiler wall & floor tube panel repair works
• Supervision services
• Replacement of old piping systems & pipeline
• Coil replacement
• Welding, fitting & installation of bridge elements , inserts
• Preparation of bridge segments, trapezoids & plates
• Flatness & distortion measurements
• Heat treatment
• Supervision / QA/ QC services
• 2nd longest bridge in Norway
• Prefabrication & installation of over 110 tons of pipes & other steel structures
• Engineering, design, civil & electrical works
• Delivery of materials
• Installation of rotating equipment & hot taps
• Modernization of 8 bitumen tanks
• Erection, scaffolding & insulation works
• Pre – Commissioning, commisioning & documentation
• Replacing 12 tons of internals of main reforming columns (supports, rings, trays, packing, active panels)
• Welding & fitting works
• Installation & repair of pipelines & instruments
• Installation of new liquid distributors & collectors
• Installation of grid layer
• Opening /closing apparatus
• Mechanical repairs, modernization of tanks
• Welding & fitting activities during shutdown
• Repair & maintenance works of recovery boiler & pipeline
• Dismantling of old piping systems, coils & other internal parts
• Replacement of composite material tubes
• Boiler wall & floor tube panel repairs
• Erection & welding of pipe spools & static equipment
• Prefabrication of pipe spools & NDT
• Installation of over 350 tons of different steel grade primary & secondary supports
• Prefabrication of over 200 tons of piping
• Installation of 70 various pumps
• Supervision / documentation
• Erection & welding of primary & secondary supports
• Erection & welding of pipe & prefabricated pipe spools
• Installation of steel constructions
• Welding of different steel grade pipes
• Installation & repair of piping
• Welding & erection works
• Preparation of static equipment ( blinding, opening, closing) for repair
• Inspection works
• Installation of over 20 tons of steel structures & new pipelines
• Activities & documentation for pre/during/post shutdown