Working place: Varobacka, Sweden
The beginning of works: 10/2015
The completion of works: 05/2016
Employees: engineers – 20 persons; fitters of different clasifications (pipe fitters, steel structure fitters, etc.) – 100; welders of different steel and grades (SS, Carbon, Duplex, Titanium) – 40 persons; support personnel (drivers, lifters, crane operators) – 25 persons.
Performed works:
- SMO piping – 1 ton;
- Titanium Grade 2 piping – 2 tons;
- Conventional carbon steel piping – 4 tons;
- Duplex piping – 7 tons;
- FRP piping (plastic piping) – 20 tons;
- Stainless steel secondary supports – 77 tons;
- Carbon steel secondary supports – 5 tons;
- Primary supports – 42 tons.